Skip to content

Case studies

Three projects delivered by Soluciones Dacast, with measured results.

Case01/ 03

Solar energy · Turnkey installation · Adaptable solutions

Energy efficiency that powers operations in any environment

Integrated photovoltaic system for energy independence

A solution designed to enable and support the operations of an office in a remote location with no access to the public power grid, using an approach that can be adapted to urban facilities that need self-consumption or backup power.

14
solar panels
7.7 kWp
PV capacity
6 kW
hybrid inverter
5.12 kWh
lithium battery
  1. 01

    Demand assessment and sizing

    We carried out a detailed assessment of the requirement and worked closely with the client to size the electrical loads and understand its current and future operational needs. This analysis allowed us to define a solution matched to the expected demand, with priority on reliability and adaptability.

  2. 02

    Solution implemented

    Installation and interconnection of 14 solar panels rated at 550 W each, together with a hybrid inverter and a lithium battery storage system. The required equipment and accessories were integrated to give the office its own generation and storage.

  3. 03

    Outcome and application

    The project made it possible to set up a fully functional office in a remote area with no connection to the public grid. The same approach can be evaluated for offices, retail sites and urban facilities, depending on their loads, building conditions and self-consumption or backup needs.

Technicians mounting solar panels on the office roof
Panel installation
Solar panels installed on the roof
Installed panels
Hybrid inverter mounted on the wall above the lithium battery rack
Inverter and batteries

Case02/ 03

Data protection · Operational continuity · Virtualization

Backup and virtualization for a more resilient infrastructure

We modernized the backup and virtualization platform by integrating Veeam Backup & Replication with Proxmox VE, backup repositories, Fibre Channel connectivity and an IBM tape library.

100%
of committed scope completed
12 TB
of storage configured
2
redundant Fibre Channel paths
LTO
tape library backup
  1. 01

    Solution analysis and design

    We reviewed the technical requirements and the virtualization environment to define the backup, storage, networking and connectivity architecture. Close coordination with the client allowed us to align the deployment with its operational needs.

  2. 02

    Integrated implementation

    Proxmox VE 9 was deployed on a physical server, with virtual machines for the Veeam server and the backup repository. VLAN-segmented networks and Fibre Channel access to the IBM tape library were also configured.

  3. 03

    Protection and validation

    A hardened repository with immutability was implemented on Linux and XFS, protecting backups against modification or deletion during the configured period. This adds another layer of defense against ransomware and other incidents. Documented testing confirmed connectivity, recognition of the IBM library, tape writes, and successful reads and restores.

Enterprise backup

Veeam Backup & Replication

Immutable protection

Hardened repository and IBM tape

Virtualized infrastructure

Proxmox VE and Fibre Channel

Result

An operational, validated platform, with backup jobs configured, an immutable repository and verified recovery from tape.

Case03/ 03

Specialized technical cleaning · Data center

Specialized cleaning to protect operational continuity

Technical work in a critical environment, with particle control, HEPA-filtered vacuuming and anti-static cleaning of infrastructure, racks and surfaces, without disconnecting active cabling or working inside the servers.

449 → 59
PM2.5 particles per m³
−86.9%
reduction in measured count
HEPA
filtered industrial vacuuming
0
active cabling disconnections
  1. 01

    Assessment and planning

    We inspected the room and took an initial particle measurement to establish a baseline. The work was planned around the characteristics of the facility and the need to preserve operational continuity.

  2. 02

    Solution implemented

    We performed technical cleaning of surfaces, racks and cabinets, cable trays and accessible infrastructure using HEPA-filtered industrial vacuums, microfiber cloths and anti-static tools. Supplies specific to critical environments were used, without working inside the servers or disconnecting active cabling.

  3. 03

    Protection and validation

    A final measurement was taken and the result was documented with photographic evidence. The PM2.5 count fell from 449 to 59 particles per m³, a reduction of approximately 86.9%. The service was completed with the area operational and data center continuity preserved.

Air quality meter showing 449 PM2.5 particles before cleaning and 59 after
Particle measurement: before and after
Technicians cleaning the inside and doors of data center cabinets
Rack and cabinet cleaning
Technicians in hard hats cleaning cable trays and ceiling light fixtures
Infrastructure cleanup

Result

Data center handed over with a documented reduction in particles and improved technical cleanliness, with operational continuity preserved.

The initial analysis is free, with no commitment.

Send us your last 12 months of electricity bills and we will estimate the order of magnitude of your savings.